Prefabricated Packaged Skid Modules – Clapham Park
Clapham Park, Energy Centre
28th November 2017
Equipment Installed Within three Skid Modules:
- 5No. Gas fired module boilers
- 15No. LTHW Single head boiler shunt pumps
- 4No. LTHW Twin head circulating pumps
- 2No. 5000 litre thermal stores
- 2No. Chemical dosing units
- 1No. LTHW pressurisation unit complete with a 100 litre vertical expansion vessel and 3No. 3000 litre vertical expansion vessels
- 1No. Side stream filtration unit
- 1No. Vacuum degassing unit
- 1No. LTHW Sample cooler
- 1No. BCWS Water softener
- 1No. LTHW Plate heat exchanger
- 8No. LTHW Heat energy meters
- 5No. Gas meters