Prefabricated Packaged Plantroom – M&S Rushden Lakes
11 May 2017
UPDATE: Please see new photos showing the finished plantroom. UPDATE
Marks & Spencer, Rushden Lakes –
Prefabricated Packaged Plantroom
13 March 2017
Equipment Installed Within Plantroom:
- 1No. Gas fired boiler with an output of 285kW
- 1No. Low temperature hot water single head circulating pump
- 1No. 250 litre unvented indirect hot water calorifier
- 2No. Hot water service single head circulating pumps
- 1No. Low temperature hot water plate heat exchange with a duty of 49kW
- 1No. Vaccum degassing unit c/w a 300 litre expansion vessel
- 1No. 65mm air and dirt separator
- 1No. 6 litre dosing pot