Prefabricated Packaged Skids – University College London

University College London –
Prefabricated Packaged Skids

30 August 2017

Equipment Installed Within Seven Skid Modules:

  • 4No. Ground source heat pumps
  • 2No. Water heaters
  • 4No. Heating plate heat exchangers
  • 1No. LTHW Trench Heating pressurisation unit complete with 2No. 200 litre expansion vessels
  • 1No. LTHW Air Handling Unit pressurisation unit complete with 1No. 1000 litre expansion vessel
  • 1No. DHWS Primary pressurisation unit complete with 1No. 12 litre expansion vessel
  • 1No. CHW Primary pressurisation unit complete with 1No. 500 litre expansion vessel
  • 1No. Heat Pump CHW pressurisation unit complete with 1No. 12 litre expansion vessel
  • 1No. Three head cold water booster set
  • 8No. CHW single head circulating pumps
  • 8No. LTHW single head circulating pumps
  • 1No. LTHW Trench Heating 80mm air & dirt separator
  • 1No. LTHW Air Handling Unit 100mm air & dirt separator
  • 1No. CHW 150mm air & dirt separator
  • 1No. HWS Primary 32mm air & dirt separator
  • 1No. 10 Litre Ground source heat pump dosing pot
  • 1No. 5 Litre LTHW Trench Heating dosing pot
  • 1No. 10 Litre LTHW Air Handling Unit dosing pot
  • 1No. 6 Litre HWS Primary dosing pot

Prefabricated Packaged Plantroom – Wellington College

Wellington College –
Prefabricated Packaged Plantroom

30 August 2017

Equipment Installed Within Plantroom:

  • 1No. Three module boiler with an output of 719.4kW
  • 1No. Combined heat and power unit delivery 50 kWel and 79kWth
  • 1No. 2000 litre thermal store
  • 3No. Single head boiler shunt pumps
  • 1No. Twin head heating circulating pump
  • 1No. Single head CHP primary pump
  • 1No. Twin head buffer vessel pump
  • 1No. Heating pressurisation unit complete with 2No. 500 litre expansion vessels
  • 1No. 11 Litre dosing pot
  • 1No. 100mm Air & dirt separator

Prefabricated Packaged Skids – Apex House

Apex House, Wembley –
Prefabricated Packaged Skids

30 August 2017

Equipment Installed Within Nine Skid Modules:

  • 2No. Natural gas fired condensing boilers each with an output of 787kW
  • 1No. Combined heat and power unit delivery 70 kWel and 15kWth
  • 3No. 6000 litre thermal stores
  • 5No. Twin head heating circulating pumps
  • 1No. Dual pump LTHW pressurisation unit complete with 2 No. 1000 litre expansion vessels
  • 1No. LTHW de-gassing unit complete with a 600 litre expansion vessel
  • 2No. Plate heat exchangers each with a duty of 2100kW