Prefabricated CWS Packaged Plantroom – Fenwick, Bracknell

31 January 2017

UPDATE: Please see new photos showing the finished plantroom. UPDATE

 

Fenwick, Bracknell –
Cold Water Services Prefabricated Packaged Plantroom

 

16 November 2016

Equipment Installed Within Plantroom:

  • 1No. 10,000 litre cold water storage tank
  • 1No. 3 head cold water booster set
  • 1No. Single head wash down booster set
  • 1No. 50mm electromagnetic water conditioner

Prefabricated CHW Packaged Plantroom – Fenwick, Bracknell

31 January 2017

UPDATE: Please see new photos showing the finished plantroom. UPDATE

 

Fenwick, Bracknell –
Chilled Water Prefabricated Packaged Plantroom

 16 November 2016

 

Equipment Installed Within Plantroom:

  • 2No. CHW twin head circulation pumps
  • 1No. CHW single head circulation pump
  • 1No. CHW pressurisation unit c/w a 200 litre expansion vessel
  • 1No. 10 litre dosing pot